                            Risk Assessment Summary
| Rule | Severity | Likelihood | Remediation Cost | Priority | Level | 
|---|---|---|---|---|---|
| MSC00-C | Medium | Probable | Medium | P8 | L2 | 
| MSC01-C | Medium | Probable | Medium | P8 | L2 | 
| MSC04-C | Medium | Unlikely | Medium | P4 | L3 | 
| MSC05-C | Low | Unlikely | Medium | P2 | L3 | 
| MSC06-C | Medium | Probable | Medium | P8 | L2 | 
| MSC07-C | Low | Unlikely | Medium | P2 | L3 | 
| MSC09-C | Medium | Unlikely | Medium | P4 | L3 | 
| MSC10-C | Medium | Unlikely | High | P2 | L3 | 
| MSC11-C | Low | Unlikely | High | P1 | L3 | 
| MSC12-C | Low | Unlikely | Medium | P2 | L3 | 
| MSC13-C | Low | Unlikely | Medium | P2 | L3 | 
| MSC14-C | Low | Unlikely | Medium | P2 | L3 | 
| MSC15-C | High | Likely | Medium | P18 | L1 | 
| MSC17-C | Medium | Likely | Low | P18 | L1 | 
| MSC18-C | Medium | Probable | Medium | P8 | L2 | 
| MSC19-C | Low | Unlikely | High | P1 | L3 | 
| MSC20-C | Medium | Probable | Medium | P8 | L2 | 
| MSC21-C | Low | Unlikely | Low | P3 | L3 | 
| MSC22-C | Low | Probable | Medium | P4 | L3 | 
| MSC24-C | High | Probable | Medium | P12 | L1 | 
| MSC30-C | Medium | Unlikely | Low | P6 | L2 | 
| MSC32-C | Medium | Likely | Low | P18 | L1 | 
| MSC33-C | High | Likely | Low | P27 | L1 | 
| MSC37-C | High | Unlikely | Low | P9 | L2 | 
| MSC38-C | Low | Unlikely | Medium | P2 | L3 | 
| MSC39-C | Low | Unlikely | Low | P3 | L3 | 
| MSC40-C | Low | Unlikely | Medium | P2 | L3 |